General Fund Capital Programme Update and New Bids

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Cabinet

 

(a)          Acknowledged the performance achieved in relation to the Capital Programme Schemes substantially completed in 2018/2019, summarised at Appendix A in the report;

 

(b)          Considered the capital programme bids for new projects outlined in the report at Appendix B and approved the new capital schemes; 

 

(c)          Recommended to Full Council that additional funding of £545,000 be allocated from the Renewables Reserve to complete the footpath lighting upgrades given the environmental benefits, and that a full report be submitted to Cabinet for approval that outlines the programme of work, timescales, costs and payback period;

 

(d)          Recommended to Full Council that funding of £1,300,000 be allocated from the Renewables Reserve for a range of energy efficiency and green energy measures at South Cambridgeshire Hall, and that a full report be submitted to Cabinet for approval that outlines the range of modifications and enhancements proposed, costs and payback period;

 

(e)          Supported, if resources permit, the establishment of a Renewal and Repairs Fund for vehicles, plant and equipment, as part of the 2020/2021 revenue determination process; and

 

(f)           Recommended to Full Council the revised General Fund capital programme for the period 2019/2020 to 2024/2025, at Appendix C, to reflect the new scheme bids, amendments to the programme and the reprofiling of expenditure identified in the report.

Publication date: 06/11/2019

Date of decision: 06/11/2019

Decided at meeting: 06/11/2019 - Cabinet