Issue - decisions

Cambourne Section 106 Legal Agreement - Facilities and timing of provision

12/12/2005 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

RESOLVED that the embargo remain lifted for the time being, and that officers present a further progress report to the meeting of the Development and Conservation Control Committee to be held on 2nd November 2005.


07/12/2005 - Cambourne Section 106 Agreement - facilities and timing of provision

RESOLVED    that the Council reaffirm its stance in relation to seeking substantial compliance with the Section 106 Legal Agreement dated 20th April 1994, and that the Development and Conservation Control Committee request a further update at its next meeting on 4th August 2004.


17/06/2005 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

Noted, with a further update being presented to the committee meeting in August 2005. 


04/11/2004 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

Agreed as report


31/08/2004 - Cambourne Section 106 Legal Agreement - Facilities and timing of provision

RESOLVED    that the Council reaffirm its stance in relation to seeking substantial compliance with the Section 106 Legal Agreement dated 20th April 1994, and that the Development and Conservation Control Committee request a further update at its next meeting on 1st September 2004, specifying a date on which it would reimpose its embargo on planning consents for market housing should the improvement in compliance with the Section 106 Agreement not continue.


13/08/2004 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

RESOLVED    that the Council’s stance be maintained for the time being, and that a further report be received at the next meeting.


13/08/2004 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

It was RESOLVED            that the Council’s stance be maintained for the time being, and a further report to be received at the next meeting. 


13/08/2004 - Cambourne Section 106 Legal Agreement - Facilities and Timing of Provision

It was RESOLVED            that the Council’s stance be maintained for the time being, and a further report to be received at the next meeting.


04/06/2004 - Cambourne Section 106

RESOLVED    that the Council lift its embargo on the issue of planning permission, as appropriate, for further market housing in Cambourne, subject to the developers agreeing with the Local Planning Authority to devise construction programmes in all future cases where community facilities are concerned, and to the Local Planning Authority’s option, through delegation to officers and the Chairman of the Development and Conservation Control Committee, to re-impose the embargo immediately, should the need arise.


19/05/2004 - Section 106 Agreement for Cambourne - facilities update

RESOLVED    that the Council’s stance be maintained for the time being, and that a further report be received at the next meeting.