Chisholm Trail - progress report and next steps

11/11/2016 - The Chisholm Trail

The Executive Board:

 

(a)        NOTED the scheme progress being made in terms of planning approval, land procurement and stakeholder engagement.

 

(b)        APPROVED construction of phase one of the scheme, subject to gaining planning permission.

 

(c)        DELEGATED powers to approve the construction contract and selection of contractor for phase one.

 

(d)        SUPPORTED the continuation of land negotiations.

 


04/11/2016 - The Chisholm Trail

The Joint Assembly RECOMMENDED that the Executive Board:

 

(a)        Notes the scheme progress being made in terms of planning approval, land procurement and stakeholder engagement.

 

(b)        Approves construction of phase one of the scheme, subject to gaining planning permission.

 

(c)        Delegates powers to approve the construction contract and selection of contractor for phase one to the Cambridgeshire County Council’s Executive Director of Economy, Transport and Environment, in consultation with the Chairman and Vice-Chairman of the Executive Board.

 

(d)        Supports the continuation of land negotiations.